FE REVIEWER 2
Field office and living quarters shall be constructed within ___ months upon the commencement of the Works.
1 month
2 months
3 months
4 months
Field Office and other facilities provided by the contractor shall be within the ___ radius or preferably near the job site.
3 km
4 km
5 km
2.50 km
Based on survey and staking requirements, when the centerline horizontal curve radius is less than or equal to 150m and vertical parabolic curve radius is less than or equal to 100m, cross-sections shall be taken at a maximum centerline spacing of ___.
5.0 m
10.0 m
15.0 m
20.0 m
Based on Survey and Staking requirements, when the centerline horizontal curve radius is greater than 150m and vertical parabolic curve radius is greater than 100m, cross-sections shall be taken at a maximum centerline spacing of ___.
5.0m
10.0m
15.0m
20.m
If the slag is used in structural concrete, its density shall not be less than ___.
1120 kg/m
980kg/m
1150kg/m
960kg/m
Fly Ash, if specified or permitted as a mineral admixture, it shall not exceed __ partial replacement of Portland Cement in concrete mix.
5.0%
10%
15%
20%
What is the maximum stacking layer of cement if the storage period is more than 60 days?
10 layers
7 layers
12 layers
14 layers
What is the maximum stacking layer of cement if the storage period is less than 60 days?
10 layers
7 layers
12 layers
14 layers
For timber forms, it is important that the moisture content of the timber that will be used to make the formwork in between ___(ME march 2023 Exam).
10 - 15%
5-10%
10-15%
15-20%
What is the minimum thickness used for metal forms or of such thickness that the forms remain true to shape?
2.5 - 3.0mm
2.0 - 3.0mm
3.0 - 5.0mm
3.5 - 4.0mm
What is the minimum wall thickness of structural steel tubes used as support for forms?
3mm
2mm
5mm
4mm
What is the minimum slump of Lean concrete?
30mm
25mm
50mm
75mm
All scaffolding and shoring shall be capable of supporting at least ___ the designed working loads
2 times
3 times
4 times
1.5 times
No scaffolding and shoring shall be erected to exceed __ without written permission from the DPWH Engineer
20m
30m
10m
15m
What is the minimum dimension of Elevators? IRR of BP 344
1mx1.40m
1.10mx1.40m
1mx1.50m
1.10mx1.50m
What is the maximum height of water closet? IRR of BP 344
0.45m
0.30m
0.50m
0.25m
What is the maximum height of flush control of the water closer? IRR of BP 344
1.0m
1.20m
0.80
0.75m
Rock shall be excavated to a depth of __ below the subgrade within the limits of the roadbed.
100mm
150mm
200mm
250mm
What is the maximum abrasion loss in mass percent of Gravel fill to be considered as suitable embankment material?
30%
40%
50%
25%
Specific gravity of suitable rock fill embankment shall be above ___.
2.5
2.2
2.3
2.4
Embankment of earth shall be placed in horizontal layers not exceeding ____.
100mm
150mm
200mm
250mm
When embankment dimensions are less than ___, the DPWH engineer may waive the construction compaction trials
10mx50m
5mx10m
10mx10m
10mx15m
Samples of the fine and coarse aggregates to be used shall be selected by the DPWH Engineer for tests at least ___ before the actual correcting operations shall begin.
20 days
30 days
12 days
15 days
Storage buildings shall have capacity for storage of a sufficient quantity of cement to allow sampling at least _ before the cement is to be used
20 days
30 days
12 days
15 days
When mixing concrete in trucks, what is the minimum mixing speed in revolution per minute(rpm)?
3 rpm
4 rpm
5 rpm
6 rpm
When mixing concrete in trucks, what is the maximum mixing speed in revolution per minute? (RPM)?
3 rpm
4 rpm
5 rpm
6 rpm
When placing concrete by pumping, what is the minimum discharge capacity of the equipment?
1.50 m3/hr
3.0 m3/hr
5.0 m3/hr
10.0 m3/hr
When placing concrete by pumping what is the maximum discharge capacity of the equipment?
1.50 m3/hr
3.0 m3/hr
5.0 m3/hr
10.0 m3/hr
When placing concrete by pumping, what is the minimum pressure capacity of rh
0.3 MPA
0.4 MPA
0.5 MPA
0.6 MPA
When placing concrete in the water what is the minimum diameter of the tremie tube? (PAST ME EXAM)
100mm
150mm
300mm
250mm
This the slump to be maintained when placing concrete in water.
3-5cm
4-8cm
5-8cm
6-8cm
What is the minimum cement content of concrete Class Seal?
380 kg/m3
400 kg/m3
350 kg/m3
300 kg/m3
The concrete in wall, beams, columns, and the like shall be placed in horizontal layers not more than __ thick.
100mm
150mm
300mm
250mm
High Strength alloy steel bar for post-tensioning shall be proof stress to ___ of the granted tensile strenght
80%
90%
85%
95%
What is the minimum distance between reinforcing steel bars?
40 mm
20 mm
30 mm
50 mm
Lap splices shall not be permitted for bars large than __
28 mm
32mm
36mm
25mm
The overlapping of Bar Mat shall not be less than ___ in width
1 mesh
2 mesh
3 mesh
2.5 mesh
What is the maximum engine capacity of the motorized banca if provided in the project contract (vehicle)?
30 hp
40 hp
50 hp
60 hp
If pick up type service vehicle is provided in the project contract, the engine displacement shall not exceed ___ for gasoline and 3,000 L for diesel and/or shall not have an engine exceeding 4 cylinders.
2,500 L
3,000 L
4,000 L
2,000 L
What is the maximum transverse spacing between stakes?
3.0m
4.0m
5.0m
6.0m
When the centerline horizontal curve radius is greater than 150m and vertical parabolic curve radius is greater than 100m, the maximum distance between centerline points shall be ___.
30m
20m
10m
15m
No other billboards shall be allowed to be installed ___ before and ____ after all DPWH projects and in-between the projects limits or within the road right-of-way.
300m
200m
100m
150m
At least how many days the Alternate traffic control plans should be submitted before intended use?
20 days
30 days
12 days
15 days
Where structures are to be founded directly on rock, the length of rock core should be not less than __ & extended further if the use of socketed piles or drilled shafts are anticipated.
3m
4m
5m
6m
For retaining walls more than 30m in length, the spacing between borings should be no greater than ____ or fraction hereof.
30m
40m
50m
60m
For cuts more than ___ in length, the spacing between borings along the length of the cut should generally be between 60 and 120m
30m
40m
50m
60m
At critical locations and high cuts, provide a minimum of __ in the transverse direction to define the existing geological conditions for stability analysis.
2 borings
3 borings
4 borings
1 boring
For buildings with basements, the depth of boring should extend to ___ the least dimension of the structure's footprint added to the depth of basement.
2 times
3 times
4 times
1.5 times
Which of the following is prohibited as drilling fluid additives in soil investigation?
Lubricants
Foamers
Emulsifiers
Diesel Fuel
Soil Penetration Test shall be performed at 450mm sampling depth every ____ interval until the desired depth is attained.
3.0m
2.0m
1.0m
1.5m
For scaffolding and shoring works, what is the minimum width of any work level?
0.30m
0.40m
0.50m
0.60m
All Scaffolding and shoring work levels 10m or higher above ground or floor level, shall have a 100mm toe board and handrails no less than ___ or more than 1.07m high with a mid-rail
0.915m
0.815m
0.715m
0.515m
What is the minimum thickness of aluminum sheeting used for Sign panels (Signages)?
3.0 mm
2.0 mm
1.0 mm
1.5 mm
What is the maximum rise of every step in a stairway? BP 344
300 mm
200 mm
100 mm
250 mm
What is the minimum run of every step in a stairway? BP 344
300mm
200mm
100mm
250mm
The maximum variations in the height of risers and the width of treads in anyone flight shall be___.
3 mm
2mm
5 mm
4 mm
Clearing shall extend ___ beyond the toe of the fill slopes or beyond rounding of cut slopes as t he case maybe for the entire length of the project.
1m
2m
3m
4m
All materials for excavation shall be classified as follows except:
Unclassified Excavation
Rock Excavation
Peat Excavation
Muck Excavation
Basis of payment of structure excavation is the volume outside of vertical planes ____ outside of and parallel to the neat lines of footings and the inside walls of pipe and pipe-arch culverts at their widest horizontal dimensions.
300 mm
250mm
450mm
350mm
The placing of individual rocks and boulders greater than 600mm in diameter shall be permitted provided that when placed, they do not exceed ___ in height
1.0 m
1.2 m
1.50 m
2.0 m
In areas affected by tidal action(rise and fall of water level) such as seabed, estuary, coastal area, etc. What is the basis of all elevation Computations?
MLLW
MLWL
WLLM
MLWL
In areas not affected by tidal actions such as riverbeds, floodway channel, creek or estero, etc. All elevations shall be referred to a ___ of known coordinates and elevation based on Mean Sea Level(MSL) established by the National Mapping and Resource Information Authority(NAMRIA).
BM
Am
CM
PM
The bench marks a generally located at about ___ interval along national provincial, and municipal roads.
1.0 km
2.5 km
2.0 km
3.0 km
What is the maximum permissible over dredging?
300mm
250mm
450mm
350mm
For reclamation, the materials above Mean Lower Low Water(MLLW) whether obtained by dredging or from borrow pits shall be spread out and compacted in Layers not exceeding _____.
300 mm
250mm
450mm
350mm
No extraction, removal and/or disposition of materials shall likewise be allowed in offshore areas within 500m distance from the coast to ___ from the mean low tide.
300m
400m
500m
200m
What class of concrete is used for thin reinforced sections, railings, precast R.C piles and cribbing and for filler in steel grid floors?
Class A
Class B
Class C
Class P
What class of concrete is used for Prestressed concrete structures and members?
Class A
Class B
Class C
Class P
For structural concrete, the Maximum size aggregate (MSA) shall be or not larger than _____ of the narrowest dimensions between sides of forms of the member for which the concrete is to be used nor larger than ____ of the minimum clear spacing between individual reinforcing bars or pre-tensioning strands.
1/2 & 3/4
3/4 & 3/4
1/5 % 3/4
1/5 & 2/3
If the coarse aggregate is subjected to 5 cycles of the sodium sulfate soundness, what is the maximum weighted loss?
10 mass %
12 mass %
15 mass %
5 mass %
What is the maximum mass percent of wear of Coarse Aggregates for structural concrete?
30
25
40
35
For lean Concrete to be placed prior to placing of reinforcing steel bar of any prefabricated structure shall have a minimum compressive strength of ____ the required strength of 13.8 MPa at 7 days.
75%
80%
85%
90%
Lapped splices will not be permitted at locations where the concrete sections are insufficient to provide minimum clear distance of ____ the maximum size of coarse aggregate between the slice and the nearest adjacent bar.
1 1/3
2 1/3
3 1/3
3/4
Concrete pouring of structural slab must have at least 20.7 MPa compressive strength at 28 days with a minimum thickness of 50 mm to a maximum of ____.
75 mm
80 mm
90 mm
100 mm
What is the minimum seating clearance of the joist if laid on steel I-beams?
100mm
38mm
50mm
75mm
What is the class of Concrete filler for rocks bulkheads when required for the purpose of preventing the escape of fill material?
Class A
Class B
Class C
Class D
Concrete filler for rocks bulkheads when required for the purpose of preventing the escape of fill material, shall be Class ___ concrete plus ____ additional cement conforming to the requirements given under Item 900, Structural Concrete for the class given.
Class A, 10%
Class B, 10%
Class B, 5%
Class C, 5%
Rocks shall not be out of line on the faces of the bulkheads by more that __.
100mm
150mm
50mm
75mm
In excavation for water supply system, which workers may be required to enter, excavated or other materials shall be stockpiled temporarily at least ___ m from the edge of the trench
600mm
650mm
500mm
750mm
For Pipeline Trench Excavation, what is maximum amount of open trench permitted at any time and in one location?
100m
50m
25m
75m
For Pipeline Trench Excavation, the bottom of the trench, including any shoring, shall have a minimum width equal to the outside diameter of the pipe plus _____.
300mm
600mm
500mm
750mm
For Pipeline Trench Excavation, the bottom of the trench, including any shoring, shall have a maximum width equal to the outside diameter of the pipe plus ____.
300mm
600mm
500mm
750mm
Backfill materials shall be laid in horizontal layers, what is its maximum thickness?
150mm
200mm
100mm
250mm
Backfill materials shall be laid in horizontal layers, what is its maximum compacted density and to be carried to the level of the surrounding ground?
95%
90%
100%
97%
When curing concrete by waterproof Membrane Method, what is the minimum period the curing membrane shall remain in place?
24 hrs
48 hrs
60 hrs
72 hrs
If the curing compound has not been used within ____ after the date of manufacture additional testing may be required before the use to determine compliance to requirements.
60 days
90 days
120 days
30 days
Curing compound shall be applied with a pressure spray shall be of such character that it will harden ____ after application
60 minutes
90 minutes
120 minutes
30 minutes
What is the pipe lining thickness tolerance
-+ 25%
-+ 35 %
-+ 20%
-+30 %
What is the minimum pipe coating thickness as per Item 1602 Pipeline system?
15 mm
20 mm
20 mm
25 mm
All polyethylene pipes shall be rated for use with water at 23C and a minimum working pressure of ____.
2.0 MPa
1.5 MPa
1.10 MPa
1.20 MPa
Water Treatment Plant shall include any of the following treatment except:
Thickening
Mechanical Dewatering
Non-Mechanical Dewatering
Non-Thermal Treatment
Which of the following is not a type of Valve used for water supply system?
Gate
Globe
Butterfly
Elephant
What is the maximum Plasticity index of ill and backfill material?
6
12
25
30
What is the maximum liquid limit of fill and backfill material?
6
12
25
30
The Contractor shall provide within ___ upon issuance of the Notice to Proceed(NTP), the vehicles listed in the Contract for the exclusive use of the DPWH Engineer.
30cd
45cd
60cd
90cd
What is the minimum roadway lane width when accommodating traffic during work?
2.1m
2.5m
3.1m
3.0m
For cuts, borings should extend a minimum of __ below the anticipated depth if the cut at the ditch line.
5.0m
2.5m
3.0m
1.5m
For piles bearing on rock, a minimum of ____ rock core shall be obtained at each exploration point location to verify that the boring has not terminated on a boulder.
5.0m
2.5m
3.0m
1.5m
Under storm drainage and sewerage system, what is minimum wall thickness of a steel septic tank?
2.77mm
3.77mm
4.77mm
3.50mm
When installing pipes for drainage and sewerage systems, what is the minimum bedding thickness?
1/2 of pipes diameter
1/4 of pipes diameter
1/3 of pipes diameter
1/5 of pipes diameter
What is the minimum number of compartments for septic tank?
1
2
3
4
Water supply pipes shall be galvanized iron pipe schedule ___.
100
20
80
40
When conducting a water test on the plumbing system, the water shall be kept in pipe system or in the portion under test, for at least ___ before inspection starts.
30 minutes
15 minutes
20 minutes
45 minutes
When conducting drainage system test, the system shall hold the water for a full ___ during which time there shall be no drop greater than 102 mm.
30 minutes
15 minutes
20 minutes
45 minutes
Powder Termiticide shall not be used if rain is expected to occur within___ of application
12 hours
6 hours
24 hours
48 hours
For low penetration and sloping sites, how depth is the surface to be scarified before applying toxicants?
25 mm
50 mm
75 mm
100 mm
When soil shows termite infestation, the building area shall be thoroughly drenched with Type I working solution at the rate of ___.
12 L/m2
6 L/m2
24 L/m2
8 L/m2
When soil shows no termite infestation, the area shall be applied with Type I working solution at the rate of _____/
12 L/m2
6 L/m2
24 L/m2
8 L/m2
What method of soil poisoning is to be used when there is no visible evidence of termite infestation.
Cordoning
Drenching
Confining
Soaking
What method of soil poisoning is to be used when the soil shows visible evidence of termite infestation?
Cordoning
Drenching
Confining
Soaking
Maximum diameter of reinforcing bars shall not exceed ___ of the total thickness of slab.
1/8th
1/5th
1/6th
1/7th
What is the maximum allowable stress used when designing a PVC Sheet pile structure?
22 MPa
15 MPa
50 MPa
34 MPa
What is the minimum tensile strength of PVC Sheet pile?
22 MPa
70 MPa
50 MPa
34 MPa
What is the minimum flexural strength of PVC Sheet pile?
22 MPa
70 MPa
50 MPa
34 MPa
What is the concrete class used for Concrete Piles?
Class A
Class B
Class C
Class D
Pieces of concrete not exceeding ___ can be used as embankment
0.20 sqm
0.15 sqm
0.10 sqm
0.25 sqm
What is the over dredging tolerance of Item 1703, Dredging for flood and River Control Structures?
200mm
300mm
250mm
350mm
For Pea Gravel, there should be 1 Grading test for ___ per source of fraction thereof.
Every 500 m3
Every 250 m3
Every 300 m3
Every 75m3
For Fine and Coarse Aggregates, There should be 1 Grading test for ___ per source of fraction there of.
Every 500 m3
Every 250 m3
Every 300 m3
Every 75 m3
For fine and Coarse Aggregates, there should be 1 Quality test for ___ per source or fraction thereof.
Every 1500m3
Every 2500m3
Every 3000m3
Every 1000m3
During Air Testing for Storm Drainage Systems, the pressure shall be held without introduction of additional air for a period of not less than ____.
10 minutes
15 minutes
20 minutes
25 minutes
During Water testing for Storm Drainage Systems, Water shall be kept in the system or in the portion under test for not less than ___ before inspection starts.
10 minutes
15 minutes
20 minutes
25 minutes
Manufacturer of Chemical toxicants used for Termite Control Shall be accredited by the Department of Health(DOH) through ____
FDA
PDEA
NBI
PNP
For Liquid Termiticide Concrete, the concentrate shall be diluted with water in the proportion of 1L of concentrate material to ___ of water.
50 L
65 L
60 L
70 L
Rocks weighing 2.5 tons and above used for Rockworks are classified as:
Class I
Class II
Class III
Class IV
Which of the following shape of rocks is acceptable for Rockworks?
Rounded
Angular
Well-Rounded
None OTA
Splices of Reinforcing Steel Bars shall be staggered as far as possible and with minimum separation of not less than ___ diameters.
40 bar
50 bar
60 bar
75 bar
Epoxy coated reinforcing steel bars shall be applied with protective epoxy coating by the electrostatic spray method to strengthen the concrete and protect against corrosive conditions. No case shall application of the coating be delayed more than ____ after cleaning.
2 hours
3 hours
5 hours
6 hours
Which of the following is not a Concrete Surface Finishing?
Float Finish
Trowel Finish
Concrete Rubbed
None of the Above
When Transporting and Delivery of Mixed Concrete, the maximum temperature of concrete produced with heated aggregates, heated water, or both, shall at no time during its production or transportation exceed ____.
30C
40C
25C
35C
When a truck mixer or agitator is used for transporting concrete to the delivery point, discharge shall be completed within 1 hour or before ____ revolutions of the drum or blades, whichever comes first, after the introduction of the cement to the aggregates.
250 Rev
150 Rev.
200 Rev.
300 Rev.
When mixing Concrete at Site, all concrete shall be mixed for a period of not less than ____ after all materials, including water, are in the mixer.
60 sec
45 sec
120 sec
90 sec
During delivery of Concrete, what is the maximum interval between deliveries of batches?
10 minutes
15 minutes
20 minutes
30 minutes
Volumetric measurement shall be used only if the batching plant located more than ___ travel from the project site
1.0 hr
1.5 hrs
2.0 hrs
2.5 hrs
Stockpiling of embankment material shall not be situated within __ of a watercourse or permanent structure.
30 m
40 m
25 m
35 m
For embankment, what is the minimum area for compaction trials?
300 sqm
500 sqm
250 sqm
350 sqm
Removal of undisturbed stumps and roots and nonperishable solid objects with a minimum depth of ___ below subgrade or slope of embankment is not required.
1.0m
2.0m
2.5m
1.5m
1 Quality Test of Concrete Pipes for every ___ pcs.
100 pcs
200 pcs
25 pcs
50 pcs
1 Slump Test for every ___ Trucks
1 truck
2 trucks
3 Trucks
5 Trucks
{"name":"FE REVIEWER 2", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"Field office and living quarters shall be constructed within ___ months upon the commencement of the Works., Field Office and other facilities provided by the contractor shall be within the ___ radius or preferably near the job site., Based on survey and staking requirements, when the centerline horizontal curve radius is less than or equal to 150m and vertical parabolic curve radius is less than or equal to 100m, cross-sections shall be taken at a maximum centerline spacing of ___.","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}
More Quizzes
Challenge Your Knowledge in Philosophy and Physical Activity
10524
320
Career quiz
1260
Pawsonality Style Assesment
1890
Discover Your Trustworthy Personality: Take Our Free!
201033386
What Singer Am I? Discover Your Inner Pop Diva
201027439
Wigs & Hair Additions: Identify Remy Hair & More
201028912
What's Your Unique Writing Style? Free to Discover Yours
201030593
Can You Spot the Cardinal Sign of Overhydration? Paramedic
201052736
ITTO Project Management: Ace Your PMP Integration
201023938
Ultimate BDS: Test Your Skull & Facial Anatomy
201039262
Songs for Me: Which Track Best Fits Your Life?
201028912